Officials in White County are running into pushback from residents on a rezoning request that could lead to a data center coming to the area near Wolcott.
White County Commissioners say the land was always meant to be zoned for industrial use, and there’s been sustained interest from data center developers. The area is near Interstate 65 and located right on an electrical substation.
On Monday, the county’s plan commission narrowly gave a favorable recommendation to rezone the approximately 287 acres. The rezoning question now goes to the county commissioners for their final approval Aug. 18.
But community members, including some elected officials, aren’t happy with the process, saying the county’s economic development arm is pushing the project with little transparency. They also question whether the western edge of the county has enough water to sustain a data center.
“In my eyes, this company is actually calling the shots for who gets to attend what meetings in White County,” said Ray Anderson, who lives in the village of Lee. “They’re in control and they own no property. They have no contract signed other than NDAs. Kind of blows me away.”
Shovel ready
The land in question is part of the Mid-America Commerce (MAC) Park west of Wolcott. The MAC Park was envisioned as an industrial hub in the early 2010s to match the county’s comprehensive plan, but White County Commissioner Mike Smolek said the 250-plus acres now in question were never properly zoned.
The area is attractive to developers given the wealth of nearby substations and electric lines, and Smolek said there’s been interest for a few years. Conversations have heated up in the past few months, prompting county leaders to work with the landowners to get the land “shovel-ready.”
“Data centers are a big thing in our county. We have an abundance of electricity, and so we’ve had three or four companies come in and ask questions. That was a possibility that could happen out there,” Smolek said.

Smolek said there are now two developers “that are actively trying to pursue” a data center project in White County. Fellow commissioner Kaleb Pass told audience members at a public meeting in July the county is talking to two data center developers, though one is a “forerunner,” but added there are other projects in the mix.
Both commissioners emphasized the upcoming rezoning vote is a necessary first step for any development on that land—not an approval for any specific project.
“Everybody [Monday] night was upset and they think that we’re just going forward with this, but we have special regulations in our area plan manual on data centers,” Smolek said.
‘Secretive stuff’
Opponents of the rezoning have packed the last two plan commission meetings and have started a Facebook group titled “White County Indiana Against Data Centers.”
Anderson—a frequent poster on the page and chair of the White County Democratic Party—said he’s upset at the lack of transparency from elected officials regarding the whole process.
He dislikes that multiple officials have signed non-disclosure agreements with potential developers and isn’t a fan of commissioners holding three closed-door meetings since mid-June specifically to discuss development negotiations.
Commissioners Mike Smolek and Kaleb Pass have said publicly they are under non-disclosure agreements. Commissioner David Davis did not respond to an interview request from Inside INdiana Business.
Anderson’s sentiment extends across the political aisle, as Republican County Councilor Joanne Mosher also says she’s concerned about how few details are known publicly as the rezoning request moves along.
“There is no reason any issue needs to be hidden from the public,” Mosher said. “If a business is good enough to come into our county, they are good enough to put up a sign and say, ‘We are coming into your county. This is who we are and we’re happy to serve you.’ We do not need all of the secretive stuff.”
Another major concern is whether there’s enough water to go around if a large-scale data center comes to town. Locals say the area has longstanding water shortages, which led to the commissioning of a water table study.
Some plan commission members supported postponing rezoning talks until the study is completed, but the measure narrowly passed in a 6-4 vote.
Smolek said the Wabash Valley Power Alliance has committed to supplying electricity to any project at the MAC site.
White County Commissioners will meet Monday morning to vote on the rezoning request.