The Kentucky Public Transportation Infrastructure Authority has authorized the financial plan for the final section of the I-69 Ohio River Crossing project, connecting Evansville and Henderson, Kentucky via a new bridge over the Ohio River.
The agency also approved a resolution to enter into a bi-state development agreement with Indiana for future construction.
The project, which has been in the works since 2016, involve three sections to connect the two cities. Section 1 is the Kentucky approach to the new bridge, which started in summer 2022 and is expected to be complete by late this year. Section 3 is the Indiana approach, which began last fall and is expected to be complete in late 2026.
Section 2 is the construction of the new, four-lane bridge itself, which is being led by the Kentucky Public Transportation Infrastructure Authority. Under the development agreement, the Kentucky agency will be responsible for financing, development, construction, operation and maintenance of the bridge.
“This is a significant milestone for the new I-69 Ohio River Crossing, a key interstate connection that is going to help with the safe and reliable transit of people and goods in Western Kentucky and throughout this part of the country,” Kentucky Gov. Andy Beshear said in a news release. “This bridge is a priority for Team Kentucky and we’re taking these steps to move us closer to breaking ground and making this long-awaited connection a reality.”
While Kentucky is leading the Section 2 portion of the project, the Indiana Department of Transportation said in a statement to Inside INdiana Business that it will provide guidance and recommendations for the development of specifications and plans.
“INDOT is committed to partnering with KYTC to ensure the new I-69 Ohio River Crossing is built on schedule,” the agency said. “This step allows the bi-state project to continue moving forward toward construction.”
Section 2 of the project is estimated to cost nearly $933 million to complete. The investment is being covered by federal and state funding sources and will be supplemented by toll revenue financing.
With the bi-state development agreement signed and the financial plan approved, the Kentucky agency will begin the procurement process, with the construction contract expected to be awarded in late 2026.
Construction on the bridge is slated for completion in 2031.