Hammond Mayor Tom McDermott says a planned $7 billion data center from Chicago-based developer Decennial Group is set to continue moving forward.
According to our partners at The Times of Northwest Indiana, the project had been held up while Merrillville-based Northern Indiana Public Service Co. sought state approval to establish a subsidiary designed to provide power specifically to data centers.
The project is an expansion of the Digital Crossroads data center campus at the former State Line Generating Plant in Hammond. Decennial plans to add 450,000 square feet of space, which it will lease out to AI cloud-based computing firm CoreWeave for 20 years.
The Hammond Common Council approved a development agreement for the project in June.
According to plans filed with the Indiana Utility Regulatory Commission, Decennial plans to invest $2 billion to construct new buildings on the campus and another $5 billion in computer equipment, according to The Times.
Decennial expects to break ground on the project once agreements are in place with NIPSCO to supply power to the data center, which McDermott said are “moving in the right direction.”
Last week, the IURC approved NIPSCO’s plan to create its subsidiary, GenCo, believed to be the first in the country to be spun off by a utility company for the sole purpose of dealing with large-load customers.
With the approval, GenCo will be able to negotiate rates directly with data center developers without IURC oversight. NIPSCO says having that ability will protect residential and business customers from having to bear the brunt of any costs associated with building additional electrical capacity.
McDermott said the $7 billion investment will be the largest project in the city’s history. Decennial co-founder David Pavlik previously told Inside INdiana Business that the city has been great to work with.
“It’s a really important site. It sits on some of the densest, fastest fiber in the United States, which we made an investment to put in,” Pavlik said. “The mayor shook our hand and said, ‘I’ll stick with you if you’ll stick with us in Hammond.’ And you’ve been a phenomenal partner.”
Decennial aims to finish construction of the expansion by the end of 2028.