Northern Indiana Public Service Co. is continuing efforts to supply power to new data centers with plans for a new natural gas power plant in Jasper County.
Our partners at The Times of Northwest Indiana report the Merrillville-based utility has filed its plan with the Indiana Department of Environmental Management to build the 2,300-megawatt facility at the R.M. Schahfer Generating Station in Wheatfield.
NIPSCO spokesperson Jessica Cantarelli said the energy generated at the natural gas plant would be used to serve data centers.
“Our filing Monday confirms NIPSCO has entered into a contract to serve a data center customer,” Cantarelli said in a statement to The Times. “We do not have any additional information to share and look forward to sharing more on our third-quarter earnings call.”
The IDEM filing says NIPSCO looks to build four combined cycle combustion turbines with electrical generators and head recovery steam generators, according to the publication.
An estimated cost for the project and a timeline for construction were not given.
The utility is already set to retire its coal-fired generation units at the facility. Two years ago, plans for a $644 million natural gas peaker unit were announced for the site.