As Google withdraws its plans in Indianapolis, another next major data center project in central Indiana is getting even bigger.
On Monday, Morgan County officials gave a preliminary green light for an unnamed developer to rezone an additional 158 acres near the town of Monrovia for data center use.
The project is slated to see $1 billion of investment and previously saw close to 400 acres of farmland rezoned for light industrial use earlier this year.
As with a growing number of data center projects in Indiana, the rezoning request was met with fierce opposition from members of the public, with law enforcement almost removing a few people.
The plan commission voted 5-2 to send a favorable recommendation to Morgan County Commissioners, who have ultimate say over the rezoning.
Referred to in initial documents as “Project Louie,” the data center campus will be built on 391 acres of land in northwest Morgan County.
The site is to the east of the town of Monrovia. Its boundaries are Keller Hill Road to the north, North Antioch Road to the east, Indiana 42 to the south and West Union Church Road to the west. An AES Indiana electrical transmission line runs through the site.
The 158 acres now up for rezoning now are on the north side of the area along Keller Hill Road. About 38 acres are south of Keller Hill Road and the rest are north of it.
At the public meeting Monday, Barnes & Thornburg attorney Joe Calderon—who is representing the developer—said AES Indiana introduced the company to the new site. Calderon said the new acreage has power lines running through it and fits into the county’s comprehensive plan for the area.
“We are very cognizant of the fact that we can’t just throw a dart at a dart board and expect you as plan commission members, or the commissioners, to say, ‘Just rezone whatever you want, wherever you want.’ There is a science behind it.”
He added the additional 158 acres for the project were not part of the developer’s initial plan, but the company jumped at the chance to add contiguous acres to the campus.
Calderon also spoke to common concerns from community members saying the data center would maintain noise levels of 65 decibels at the most and have a 50-foot setback with mounds to provide a visual barrier.
Developers said they’ve completed a traffic study and are doing their due diligence on how many gallons of water the area’s aquifers can provide to the data center. If the aquifer can’t support a water-based cooling system, the company will look at an air-cooled system.
Project Louie
The new rezoning request is an addendum to the already rezoned and approved data center campus that is currently slated for four data center buildings.
In May, Morgan County Commissioners unanimously voted through a development agreement that will see the tech company pay no local taxes on qualified computing equipment purchases for a 40-year period. There will also be a 50% abatement on property taxes for 10 years on data center buildings.
In return, the anonymous company has promised to spend at least $1 billion on the facility and hire 50 employees per data center building. The local taxes are in addition to state tax breaks granted to the project by the Indiana Economic Development Corp. that could total up to $42 million over 35 years.
The company behind the project has not publicly announced itself, and many Morgan county officials have signed non-disclosure agreements.
However, tax agreements name a shell corporation called Woodland Caribou as the data center operator. That LLC is listed to the same Indianapolis address as two other shell companies associated with Google projects in Indiana.
The secretive nature of the end user was one of the points that riled up those who spoke at Monday’s meeting. Sheriff’s deputies were called to escort one speaker back to his seat after he began pointing and raising his voice at Calderon, demanding to know who was buying the land.
Meeting attendees also heckled plan commission members, leading to some tense back and forths.
“I don’t like being called a crook. I don’t like being told I’m getting things. I don’t think I’m scamming anybody. I’m up here to make a very painful point, and the accusations have not sat well with me,” said plan commission member Bill Rumbaugh before the body’s vote.
Morgan County Economic Development Corp. Executive Director Mike Dellinger said the developer likely wants to have the new zoning request squared away before revealing itself.
Morgan County Commissioners will take up the rezoning request, potentially as early as Oct. 6.