A major mixed-use project that figured to be a foundational piece of Michigan City’s revitalization will have construction delayed by several months.
The $311 million SoLa development was set to break ground in July, but our reporting partners at the Times of Northwest Indiana report the developer—Chicago-based Farpoint Development—has hit a snag securing financing.
Meeting minutes from the Michigan City Redevelopment Commission indicate the new target date for construction is the end of the year.
The SoLa project, so-called for its location “South of the Lake,” is slated to have 628,000 square feet of space and is billed as one of the largest developments in northwest Indiana. The 13-story building is expected to have 170 condos, 18 townhomes and nearly 250 hotel rooms in addition to 22,000 square feet of retail space.
The primary goal is to attract a wealthier clientele to buy a second property in the northwest Indiana locale.
The massive construction project has already seen a number of delays due to financing and rising construction costs. In March, Farpoint founding principal Scott Goodman told Inside INdiana Business construction was to begin in July and finish in early 2027.
According to The Times, Farpoint had one of its original financiers fall through, and the company is struggling at the moment to find another institution to step in.
A representative of Farpoint declined to comment.
Preliminary plans call for the SoLa’s 239 hotel rooms to be split into two hotel brands—a TRYP and The SoLa Hotel—both managed by Wyndham.